Transportation Resource Oversight Committee Meeting (Lake & Porter Counties)

Tuesday, October 23, 2018 9:00 am CST at NIRPC Office


Agenda


  1. Welcome, Pledge of Allegiance


  2. Meeting Minutes of September 18, 2018

    ACTION REQUESTED: Approval


  3. FY 19-22 Spending Plan Update

    See handout to be provided before meeting. If desired, please print a copy. NIRPC will only provide a copy upon request (please give 24 hrs notice).


  4. Project Requests

    1. Request for FY 19 ROW funds for 1173708 Crown Point – $80,000.

    2. Request for FY 19 ROW funds for 1601157 Crown point - $154,620.


  5. Letting results

    No lettings this month


  6. RTIP is Live

    See https://rtip.nirpc.org (public website) or https://rtip.nirpc.org/secure/login.asp (internal site for ERCs). Tutorial is attached.


  7. Other New Business


  8. Public Comments


  9. Adjournment. Next meeting is November 27, 2018 @ 9AM NIRPC Offices


If anyone cannot attend the meeting but would like to participate via teleconference please contact Charles Bradsky at 219-254-2509 or cbradsky@nirpc.org and request the NIRPC’s conference call in number and access code. This request must be made for each meeting and at least 24 hours in advance.

Transportation Resource & Oversight Committee Lake & Porter Counties

6100 Southport Road, Portage September 18, 2018

Meeting Minutes


In attendance were Dean Button (Hammond), Duane Alverson (Lake County), Adam McAlpine (Valparaiso), Matt Zurbriggen (Valparaiso), M. Scott Rediger (Crown Point), Jeff Huet (Schererville), Bob Thompson (Porter County), Mark O’Dell (Chesterton), Dennis Cobb and Trisha Nugent. Joyce Newland (FHWA) participated via conference phone.

NIRPC staff included Charles Bradsky, Trey Wadsworth, and Candice Eklund.


Charles Bradsky called the meeting to order at 9:02 a.m. with the Pledge of Allegiance.


Approval of Minutes

The minutes of the August 28, 2018 meeting were approved as presented on motion by Dean Button and second by Mark O’Dell.


FY 19-22 Spending Plans Ad-Hoc Committee Solution/Update

Charles Bradsky opened the discussion stating the new Spending Plan Scenario B, will be the format used going forward. The plan will continue to be available on an 11 x 17 format and will be provided at the TROC Committee meetings for review. Charles is continuing to work on balancing the budget for FY 2019, which has a deficit of $269,474 and FY2020 having a $16 million deficit.


Duane Alverson announced that Lake County will forego the local funds for DES #1702159 and bill their project locally. This includes $116,000 and $20,000 in FY 2019 funding and $391,000 in FY 2020 funding. Removing this project from the Spending Plan would reduce the deficit in FY 2019 to $133,474. The Committee agreed to use the surplus Change Order funding to balance the budget in FY 2019, which reduced the surplus from $368,810 to $235,336. The Committee discussed funding Change Order requests at 50% instead 80% in an attempt to provide funding through the fiscal year or possibly fund another project in FY 2019 if a surplus remains. It was decided to table this discussion and add it as an agenda item to the October 23, 2018 meeting. This would allow those members who were not able to attend, a chance to read the proposed changed and voice an opinion.


Duane Alverson asked if the Committee would consider funding a change order for $30,000 - $40,000 for a local bridge project in Lake County due to the state having no additional funding. Dennis Cobb showed concern because several months still remain in FY 2019 for funding requests. Duane will send Charles an email requesting Change Order funding for consideration so it could be added as an agenda item for the October 23, 2018 TROC meeting.


Project Requests

The original request on the agenda for this month was to change the year for DES #1702159 Lake County. Documented under the Spending Plan update above, Duane Alverson of Lake County stated this project can be deleted from the Spending Plan as they are foregoing local funding.

NOFA Guidelines / Instructions

Charles Bradsky presented the Northwestern Indiana Regional Planning Commission Notice of Funds Availability (NOFA) for the Fall of 2018. Dennis Cobb communicated his concerns with a NOFA in 2018 instead of 2019 due to various costs, considerations and contingencies and these will be for projects that will not be able to completed until 2023, 2024 or beyond. Most communities cannot plan that far out because of a possible change in political leadership. Trey Wadsworth spoke to the concerns of Dennis but stated there would be a NOFA in 2018 because there are some funds available and NIRPC has not had a call for project in four years. Trey also mentioned that NIRPC needs to be good financial stewards of the region’s money by having a programed TIP.


Many of the Committee members provided Charles with great feedback on the NOFA draft document. Charles Bradsky will reflect all modifications on the document, to include tracking of the changes, and distribute to the Committee next month (October) for further review and acceptance.


Dennis Cobb questioned if it would be unfair to apply the new NOFA considerations to items already in the Spending Plan in future years and that are not in the TIP. Charles Bradsky said that is a possibility and would need to be a separate agenda item added to the October 23, 2018 meeting. Currently Charles is planning on these NOFA rules only applying to all projects accepted under the next NOFA. Charles also stressed that if a project is needing to be moved before the next TIP comes out (in February 2019), to notify him with the information. The next TIP will be a five year TIP and cover the years 2020 – 2024.


Charles Bradsky also talked about the new online application. The application will be available November 19, 2018 with a completion day by January 4, 2019. Charles suggested the Committee to ask any question or setup a meeting to insure their applications are created correctly.


Letting Results

1382594 – Cedar Lake – Low bid was $1,834,216.54. NIRPC contributed $1,467,373 of Group I STBG funds to this project for construction. Since the spending plan only has $1,500,000 allocated for this project and NIRPC is required to be fiscally constrained, only $32,627 (of the $122,174) was given for CE. Charles said that he discussed this with Jill Murr of Cedar Lake, and if more funds become available, NIRPC will be willing to contribute more towards the CE. But at least something was programmed, and more funds can easily be added later.


New Business

There was no new business to discuss.


Public Comments

No public comments were discussed.


Adjournment

There being no further business, the meeting adjourned at 10:50 a.m. The next meeting will be held on October 23, 2018 at 9:00 a.m.

Northwestern Indiana Regional Planning Commission

Blue Text - Most recent proposal

MPO funds only - 2018-2021 LPA highway projects: Chicago UZA

10/2/2018

< last updated

Green Text - After discussing with municipal officials, this must stay where it is.

Includes all amendment changes & proposed amendment #10 changes

Red Text - Projects that haven't moved that are at higher risk


Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TAP/TE-TA

STBG

CMAQ

HSIP

TA

STBG

CMAQ

HSIP

TA

All sources

39

0401062

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Acquistion

STBG I

Chicago UZA

2019

2_ RR

$ 308,000

2_Low

4/6 Moved from FY 18; per INDOT/JG

$ 308,000

18 Q3 - Will move these funds to 1382661 [phase 3], but waiting until Phase 3 is ready. AM to come later.

40

1601164

Hammond

Pedestrian Flashing Beacons, Installed

at 3 trail crossings

1/18/2018

HSIP Chicago UZA

2019

3_CN

$ 23,448

1_Zero Obligated

Engineer's bid -

$232,875 low bid -

$194,390.29 NIRPC

obligated

$174,951.00 for CN

& $18,039.00 for CE

$ 23,448

$ 23,447

41

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US

20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2018

1_PE

$ 247,840

1_Zero Obligated

2/1/18 EC to get RFP and contract ASAP to obligate these funds in 2018. 4/3 scoring RFPs 4/25 moved to FY 19 per INDOT/MB

$ 247,840

18 Q3 - Had trouble getting RFP for PE. Would like to move funding to FY 19…but NIRPC does not have the funds.

42

1173595

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Pennsy Greenway P2. Main St to 137th Ave.

12/12/2018

STBG I

Chicago UZA

2019

3_CN

$ 680,960

3_ Med Funds

Q3LQR - CN est

$870,000 ($696,000 fed) CE $130,500

($104,400 fed)

$ 680,960

18 Q3 - costs are up but town will cover.

43

12/12/2018

STBG I

Chicago UZA

2019

4_CE

$ 119,040

$ 119,040

44

12/12/2018

TAP Chicago UZA

2019

3_CN

$ 387,000

$ 387,000

19 Q3 - costs are up but town will cover.

45

1173760

Schererville

Kennedy Ave

Added Travel Lanes

Kennedy Ave at Junction St. South to 67th St. and then South to US 30

12/12/2018

STBG I

Chicago UZA

2019

2_RW

$ 200,000

$ 200,000

18 Q3 - Costs are up but keep funding the same. Some funding may come from 1382603.

46

1382594

Cedar Lake

Lake Shore Drive

Intersect. Improvements (Roundabout)

at Cline Ave

9/12/2018

STBG I

Chicago UZA

2019

3_CN

$ 1,500,000

1_Zero Obligated

Q3LQR - STG3 CN est $1,722,282.09 ($1,377,825,67 fed) CE $187,500 ($122,174.33 fed)

$ 1,500,000

$ 1,500,000

18 Q3 - STG 3 revised in Permits, ROW good. Minor Q: with Hydraulics. No big issues

47

1382661

Schererville

Pennsy Greenway

Bicycle & Pedestrian Facilities

Pennsy Greenway, P3 from Wilhelm Street at Schererville Town Hall to 213th Street

3/6/2019

2019

3_CN

$ 101,162

$ 101,162

48

STBG I

Chicago UZA

$ 1,176,838

3_Med Schedule

Q3LQR - CN est

$1,397,813 ($1,118,250.40 fed) CE $199,687 ($159,749.6 fed)

$ 1,176,838

18 Q3 - Will move RR funds from 0401062. AM to come later. Some RR issues.

49

1401029

Porter County

CR 100S

Intersec. Improvement

CR 100S-2000 W of CR725 Wto 1000 E of CR 500W

3/6/2019

STBG I

Chicago UZA

2019

1_PE

$ 652,000

2_Low

$ 652,000

18 Q3 - HSIP funds?? SPMS shows $652,000 Group I funds and $427,888 Group IV funds

50

1401030

Crown Point

126th Ave (Burrell Dr)

Intersect. Improv. W/ Added Turn Lanes

From SR 55 to Court St

12/12/2018

HSIP Chicago UZA

2019

3_CN

$ 1,403,046

2_Low

CE-$155,894 fed

$ 403,046

18 Q3 - ROW is on track; 6/22 STG 3 estimate CN $1.54 M total & CE $192K total ($1,558,800 HSIP funds) Need $156K

51

PYB Chicago UZA

$ 1,000,000

52

1500323

Crown Point

US 231

Other Intersection Improvement

Courthouse Square, construct pedestrian bump-outs

7/11/2018

HSIP Chicago UZA

2019

3_CN

$ 516,380

1_Zero Obligated

Low bid CN

$529,951.1 ($24,598.40 INDOT) ($454,817 fed); CE

$68,403.34 ($61,563

fed)

$ 516,380

$ 489,380

18 Q3 - In Contracts. INDOT wants city to add ped signals; to be paid for by INDOT. Verify this when contract lets. Winning contact $529,951.10

53

1500416

Hammond

US 41

Bike/Pedestrian Bridge

over US 41 near Conkey St

7/11/2018

TAP Chicago UZA

2019

3_CN

$ 2,000,000

1_Zero Obligated

AM 9/17 Added

$494,000 for CE. Q3LQR- CN est

$4,557,408 ($2,000,000 fed) CE

$520,000 ($416,000

fed)

$ 2,043,600

$ 2,034,400

18 Q3 - $494,000 for CE given by Gary Evers (AM 9/17), but not in TIP or Spending Plan; Discuss at TROC

54

2019

4_CE

$ 494,000

1_Zero Obligated

$ 416,000

$ 416,000

18 Q3 - $494,000 for CE given by Gary Evers (AM 9/17), but not in TIP or Spending Plan; Discuss at TROC

55

1592274

Highland

Signage on multiple trails, installed

Multiple Trails; Multiple LPA's

1/16/2019

TAP Chicago UZA

2019

3_CN

$ 800,000

2_Low

$36,320 ($29,056 fed

for CE)

$ 800,000

18 Q3 - Letting moving to 1/16/19 because of NEPA doc, STG 3 due 8/24/18, RFC is 11/7/18. 18 Q4 - GTG

56

1592275

Hobart

Environmental Mitigation

Deep River Stormwater Outfall and BMP.

7/10/2019

TAP Chicago UZA (E&W)

2019

1_PE

$ 36,000

1_Zero Obligated

marcia and I to investigate

$ 36,000

18 Q3 - On Schedule

57

1592420

Merrillville

Install Signal Pre- Emption Devices 1

All signals in Hobart, Crown Point, Schererville, Merrillville, Dyer, Griffith, St. John

10/11/2018

HSIP Chicago UZA

2019

3_CN

$ 795,515

2_Low

Combined line 74

with line 75,

(2,135,869 +1017563

= 3,153,432) Q3LQR - CN est $1,752,140 ($1,576,926) CE $0

$ 795,515

18 Q3 - Minimal Risk. Move letting one month (to 10/11/18) due to agreement with RR at one location.

New estimate CN - TC $3,628,767 $2,725,616 is PYB monies. See email strings on 2/23

58

PYB Chicago UZA

$ 1,725,616

$ 1,725,616

59

Sec 164

$ 632,301

$ 632,301

60

1600418

Gary

Airport Rd

Road Rehab (3R/4R Standards)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase 3

1/16/2019

STBG I

Chicago UZA

2019

3_CN

$ 3,500,000

2_Low

verify date January 2019

$ 3,500,000

18 Q3 - Gary want to accelerate to FY 19 (April '19) but told that may not happen; TROC to discuss.

61

1600632

Gary PTC

FTA

Transfers

CMAQ Demo Operating Assistance

Broadway Express Year

#3

CMAQ Chicago UZA

2019

5_5_FL EX

$ 894,822

1_Zero Obligated

$ 894,822

62

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US 20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2019

2_RW

$ 24,000

2_Low

No ROW is needed; See Amend #10

18 Q3 - I parcel of ROW is needed, agreement with NIPSCO no purchase

63

1601147

Burns Harbor

Marquette Trail

Bike/Pedestrian Facilities

Marquette Greenway Trail, SR149 to Babcock Rd

8/5/2020

CMAQ Chicago UZA

2019

2_RW

$ 12,000

2/8/18 No ROW is needed. See Amend

#10

N/A

64

1601157

Crown Point

109th Ave

Access Control

109th Ave Access Control, Delaware Pkwy to SR 53, includes median construction

10/15/2019

HSIP Chicago UZA

2019

2_RW

$ 101,250

2_Low

could this qualify for CMAQ?

$ 101,250

18 Q3 - On schedule; City would like to accelerate if possible

65

1601159

Valparaiso

Ransom Rd

Other Type Project (Miscellaneous)

Ransom Road Safety Improvements, CR50W to CR 150W

11/15/2018

HSIP Chicago UZA

2019

2_RW

$ 23,400

RW to be eliminated Amend #10 funds to be applied to CN

N/A

66

1601159

Valparaiso

Ransom Rd

Other Type Project (Miscellaneous)

Ransom Road Safety Improvements, CR50W to CR 150W

7/11/2019

HSIP Chicago UZA

2020

3_CN

$ 476,361

3_Med Funds

Valpo requesting and additional $33,741 for CE/CN Q3LQR CN

est $465,800 ($419,220 fed) CE

$69,100 ($62,190

fed)

$ 476,361

18 Q3 - Accelerated from 11/20. City would like additional funds for Mill & Fill, & Rumble Stripes to be discussed at TROC.

67

1601161

Kouts

Regulatory & Warning Sign Replacement

Town-wide

7/11/2018

HSIP Chicago UZA

2019

3_CN

$ 40,500

1_Zero Obligated

Low bid CN

$38,594.08 ($34,735

fed); CE $9 000

$ 34,735

$ 34,735

18 Q3 - In Contracts CE? Originally put CE in with PE (big No-No) for CE is $9,100 TC ($8,190 fed) Winning bid at letting is $38594.08 ($34,735 fed)

68

4_CE

$ 8,190

1_Zero Obligated

$ 8,190

$ 8,190

69

1601162

Kouts

Pavement Markings

Town-wide

7/11/2018

HSIP Chicago UZA

2019

3_CN

$ 11,700

2_Low

No bids; to be combined in with 1601161 as a CO

$ 11,700

$ -

18 Q3 - In Contracts CE? Originally put CE in with PE (big No-No) for $9,100 TC ($7,280)


image

1

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

70

1601163

Hammond

173rd Ave

Pedestrian Island Construction

at Main Entrance to Purdue NW Campus

8/14/2019

STBG I

Chicago UZA

2019

2_RW

$ 40,000

2-Low

$ 40,000

18 Q3 - May not need; but keep on the books just in case

71

1_PE

$ 24,000

1_Zero Obligated

$ 24,000

$ 24,000

72

1601184

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #1)

CMAQ Chicago UZA

2019

5_5_FL EX

$ 332,800

1_Zero Obligated

$ 332,800

73

1601185

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #1)

CMAQ Chicago UZA

2019

5_5_FL EX

$ 275,200

1_Zero Obligated

$ 275,200

74

1601923

Portage

Willowcreek Road

Bridge Rehabilitation Or Repair

Rehabilitate Willowcreek Rd Bridge over I-80/90.

7/11/2018

STBG I

Chicago UZA

2019

3_CN

$ 640,000

1_Zero Obligated

$ 525,671

$ 525,671

18 Q3 - In Contracts. Letting Low bid $657,088.16 ($525,671 fed) CE- $0.00

75

1702158

Gary

Marquette Trail

Bike/Pedestrian Facilities

Gary Green Links/Marquette Trail. Roosevelt St to Polk St.

11/11/2020

STBG I

Chicago UZA

2019

1_PE

$ 300,000

2_Low

$ 300,000

18 Q3 - On schedule

76

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2018

1_PE

$ 116,000

2018

Eliminate the project per DA. County will do on their own. Per email on 9/20

77

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2019

2_RW

$ 20,000

3_Med

2019

18 Q3 - keep here, Revisit next LQM. Eliminate the project per DA. County will do on their own. Per email on 9/20

78

0900075

Valparaiso

Silhavy Rd

Rebuild 3R/4R

Evans Ave to LaPorte Ave

2/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 3,094,579

2_Low

*Admin Mod Mar 18* change date from FY 21 to FY 19

$ 3,094,579

18 Q3 - ROW has 2 condemnations; CN RR

79

0900075

Valparaiso

Silhavy Rd

Rebuild 3R/4R

Evans Ave to LaPorte Ave

2/6/2019

STBG I

Chicago UZA

2019

4_CE

$ 464,181

2_Low

$ 464,181

18 Q3 - ROW has 2 condemnations; CN RR

80

0900080

Portage

Central Ave

Access Control

Willowcreek Rd Intersection Improvements at Central Ave.

3/6/2019

CMAQ Chicago UZA

2019

$ 52,000

1_Zero Obligated

*Admin Mod Mar 18* change date from FY 18 to FY 19 Q3LQR- CN est $1,260,000 ($1,008,000 fed) CE

$189,000 ($151,200

fed)

$ 52,000

$ 52,000

Admin Mod 9/17 added funds to this project. From $1,089,760 to $1,152,000 (fed) 18 Q3 - ROW in Condemnation; STG3 6/18;

81

3_CN

$ 1,152,000

4_High Schedule

$ 1,152,000

82

1801359

NIRPC

CMAQ Planning

Public Education SFY 2019

CMAQ Chicago UZA

2019

6_6_6_ UPWP

$ 360,000

1_Zero Obligated

$ 360,000

83

1172007

Lake County

45th Ave

Added Travel Lanes

45th Ave. from Whitcomb to Chase (Ph 2B)

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 1,752,000

4_High Schedule

high risk for FY 19; CN est $1,950,000 ($1,560,000 Fed) CE

$243,750 ($192,000

fed)

$ 1,752,000

18 Q3 - Lake County wants to move to FY 20; need to verify ROW amounts

84

1401034

Hobart

Colorado St

Line of Sight Corrections; Access Management

North of US 30

1/15/2020

HSIP Chicago UZA

2020

2_RW

$ 56,250

4_High Funds

Amend #10 added phase

$ 56,250

18 Q3 - ROW current needs equal $195,000. 18 Q4 - Project costs are starting to escalate. ROW- 4X; CN- 2X. Advised to talk to INDOT since they control this intersection.

85

1592273

Lowell

Bicycle & Pedestrian Equipment

Up to 20 Bicycle Racks

CMAQ Chicago UZA

2019

1_PE

$ 1,600

2_Low

to be moved to 2019 per MB. Need to be put into Admin Mod 4/3

$ 1,600

18 Q3 - Town still wants to continue but informed that there may not be funds.

86

1601158

Crown Point

109th Ave

Intersect. Improvements (Roundabout)

at Iowa St

7/14/2021

HSIP Chicago UZA

2019

2_RW

$ 112,500

4_High Schedule

If PE is in late 2018 & CN is in 2022, RW probably will be moved out to 2020

$ 112,500

18 Q3 - City would like to move this phase to FY 20

87

0710056

Munster

45th St

Railroad Grade Separation & Added Travel Lanes

Reconstruction of 45th St from 0.2 mi E of Calumet Ave to Calumet Ave

3/6/2019

PYB Chicago UZA

2019

3_CN

$ 6,980,644

4_High Schedule Complexity

$ 6,980,644

18 Q3 - INDOT, RDA, NIRPC funds. Moving along, USPs better; big issue with shoefly (RR want town to build, INDOT feels not a good idea). If it getts bumped, it will probably be to FY 22 or 23.

88

0710056

Munster

45th St

Railroad Grade Separation & Added Travel Lanes

Reconstruction of 45th St from 0.2 mi E of Calumet Ave to Calumet Ave

3/6/2019

STBG I

Chicago UZA

2019

3_CN

$ 2,619,356

4_High Schedule Complexity

*Admin Mod Mar 18* change date from FY 18 to FY 19

$ 2,619,356

18 Q3 - INDOT, RDA, NIRPC funds. Moving along, USPs better; big issue with shoefly (RR want town to build, INDOT feels not a good idea).


image

2

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

89

1006787

Merrillville

Mississippi St

Added Travel Lanes

93rd Ave to 101st Ave

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 3,612,000

4_Funds

Amend #10 added phase CN est

$4,516,000 ($3,612,000 fed) CE

$0

$ 3,612,000

18 Q3 - Good. Minimal risk to schedule, funds or scope. Candidate for Plan B 2019 letting. 18 Q4 - Town would like to move this project back one year to come up with the money and get more life out of pavment.

90

1173707

Munster

Pennsy Greenway

Bicycle & Pedestrian Facilities

Construct Pennsy Greenway Trail from Fisher St at Timrick Dr to Calumet Ave north of 45th St

7/10/2019

CMAQ Chicago UZA

2020

3_CN

$ 555,040

2_Low

$ 555,040

18 Q3 - Need a new estimate since project is being tweaked and may combine with 1173597. Funds may move to 1173597 and move to 2022.

91

1173760

Schererville

Kennedy Ave

Added Travel Lanes

Kennedy Ave at Junction St. South to 67th St. and then South to US 30

2/5/2020

STBG I

Chicago UZA

2020

3_CN

$ 4,206,472

2_ Low Funds

Q3LQR- CN est

$5,834,000 ($4,206,472[72%]) CE $875,000 ($0 fed)

$ 4,206,472

18 Q3 - Costs are up but keep funding the same. Some funding may come from 1382603.

92

1500221

Hammond

Chicago Ave

Added Travel Lanes

from IN/IL State Line to Marble St

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 9,400,000

2_Low

Q3LQR- CN est

$10,000,000 ($8,355,556 fed) CE

$1,305,556 ($1,044,444 Fed) =

$11,791,713($9,433,

369 fed)

$ 9,400,000

18 Q3 - Funds for RR are in PE

93

1592275

Hobart

Environmental Mitigation

Deep River Stormwater Outfall and BMP.

7/10/2019

TAP Chicago UZA

2020

3_CN

$ 246,480

2_Low

$ 246,480

18 Q3 - On track. 18 Q4 - Cost are expecting to rise.

94

1601146

East Chicago

Marquette Trail

Bike/Pedestrian Facilities

from Indinapolis Blvd. (US

20) to Kennedy Ave

10/15/2019

CMAQ Chicago UZA

2020

3_CN

$ 828,000

3_Med Schedule

Amend #10 added phase

$ 828,000

18 Q3 - Letting needs to move to FY21.

95

1601157

Crown Point

109th Ave

Access Control

109th Ave Access Control, Delaware Pkwy to SR 53, includes median construction

10/15/2019

HSIP Chicago UZA

2020

3_CN

$ 1,098,000

2_Low

*Admin Mod Mar 18* LQR, SPMS shows letting is 10/9/19 (in 2021 TIP) CN est

$1,220,000 ($1,098,000 Fed) CE

$152,000 ($122,000

Fed)

$ 1,098,000

18 Q3 - City would like to accelerate if possible.

96

1601163

Hammond

173rd Ave

Pedestrian Island Construction

at Main Entrance to Purdue NW Campus

8/14/2020

STBG I

Chicago UZA

2021

3_CN

$ 792,000

3_Med Funds

Q3LQR- CN est

$573,913 ($459,130 fed); CE $56,087

($68,870 fed)

$ 792,000

18 Q3 - City requesting additional funds for scope revision (bus turnout spot) PE and CN.

97

1601165

Gary

Regulatory & Warning Sign Replacement

City-wide

7/10/2019

HSIP Chicago UZA

2020

3_CN

$ 450,000

2_Low

$ 450,000

18 Q3 - RFP in process

98

1601184

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #2)

CMAQ Chicago UZA

2020

5_5_FL EX

$ 326,400

1_Zero Obligated

$ 326,400

99

1601185

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #2)

CMAQ Chicago UZA

2020

5_5_FL EX

$ 269,600

1_Zero Obligated

$ 269,600

100

1601726

Winfield

Randolph St

Other Type Project (Miscellaneous)

Randolph St HAWK Signal (2000' S of 109th)

8/7/2019

HSIP Chicago UZA

2020

3_CN

$ 70,200

3_Med Funds

$ 70,200

18 Q3 - All projects on one CN contract. CN cost increased from TC $78,000 ($70,200 fed) to TC $125,000 ($112,500 fed). Candidate for Plan B 2019 letting.

101

1601727

Winfield

Randolph St

Other Type Project (Miscellaneous)

Randolph St School Zone Flashers (3000' & 4000' S of 109th)

8/7/2019

HSIP Chicago UZA

2020

3_CN

$ 9,000

3_Med Funds

$ 9,000

18 Q3 - All projects on one CN contract. CN cost increased from TC $10,000 ($9,000 fed) to TC $16,000 ($14,400 fed). Candidate for Plan B 2019 letting.

102

1601728

Winfield

109th Ave

Signage, New or Replacement

109th Ave Signage Improvements (109th, 5600' W of Randolph)

8/7/2019

HSIP Chicago UZA

2020

3_CN

$ 5,400

3_Med Funds

$ 5,400

18 Q3 - All projects on one CN contract. CN cost increased from TC $6,000 ($5,400 fed) to TC $8,000 ($7,200 fed). Candidate for Plan B 2019 letting.

109

1500417

Hobart

Bicycle & Pedestrian Facilities

in vicinity of Hobart Middle School

8/19/2019

TAP Chicago UZA (SRTS)

2020

3_CN

$ 247,200

3_Med Schedule

*Admin Mod Mar 18*

Q.R. & SPMS shows letting is 8/19/19 (in 2019 TIP)

$ 247,200

18 Q3 - INDOT has issues with Archelogical Report; Probably move 8 months to April 2020. 18 Q4 - Keep in FY 20 per mayor.

103

1702159

Lake County

101st Ave

Signals, New or Improved

101st Ave New Signals at Sheffield Ave.

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 391,000

3_ Med Schedule

Q3LQR- CN

$500,000 ($400,000

fed) CE $75,000 ($3,000 fed)

$ -

18 Q3 - keep here, Revisit next LQM. Eliminate the project per DA. County will do on their own. Per email on 9/20

110

0710064

Gary

15th Ave

Signals, New or Upgraded

Multiple locations at/near intersection of 15th Ave and MLK Dr,

7/14/2021

STBG I

Chicago UZA

2020

2_RW

$ 160,000

4_High Scope

18-14; #17

$ -

111

1600418

Gary

Airport Rd

Road Rehab (3R/4R Standards)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase 3

1/16/2019

STBG I

Chicago UZA

2020

2_RW

$ 160,000

4_High Scope

18-14; #17

$ 160,000

18 Q3 - Gary to rescope

104

1801359

NIRPC

CMAQ Planning

Public Education SFY 2020

CMAQ Chicago UZA

2020

6_6_6_ UPWP

$ 360,000

1_Zero Obligated

$ 360,000

105

1173430

Portage

Central Ave

Road Reconstruction (3R/4R Standards)

Central Ave. reconstruction from Lake/Porter Co. Line to Willowcreek Road

7/8/2020

STBG I

Chicago UZA

2020

2_RW

$ 200,000

4_High Scope

*Admin Mod Mar 18* change date from FY 18 to FY 20

$ 200,000

18 Q3 - project will be split in tow or more phases by next LQM.

106

1172078

Gary

Ridge Rd

Road Reconstruction (3R/4R Standards)

Ridge Road Reconstruction, Connecticut St to Mississippi St. Phase 2

7/10/2019

STBG I

Chicago UZA

2020

3_CN

$ 5,060,000

4_High Scope

18-14; #17

$ -

18 Q3 - Gary to rescope

107

1382598

Hobart

County Line Rd

Road Reconstruction (3R/4R Standards)

from US 6 to Cleveland Ave

10/7/2020

STBG I

Chicago UZA

2020

2_RW

$ 200,000

4_High Schedule

$ 200,000

18 Q3 - NEPA doc is outstanding. FHWA & SHPO have issues. May need to move 12 months.

108

1401034

Hobart

Colorado St

Line of Sight Corrections; Access Management

North of US 30

1/15/2020

HSIP Chicago UZA

2020

3_CN

$ 734,850

4_High Funds

*Admin Mod Mar 18* LQR, SPMS shows letting is 10/19/19 (in 2021 TIP)

$ 734,850

18 Q3 - ROW current needs equal $195,000 18 Q4 - Updated ROW cost are $571,000, updated CN cost is

$1,620,000 18 Q4 - Project costs are starting to escalate. Advised to talk to INDOT since they control this intersection.


image

image

3

Row ID

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

Phase

In TIP or SPMS

Only

Risk

Comments

TIP 2019

Actual Obligated 2018

TIP 2020

TIP 2021

2022

Post-TIP

Quarterly Notes / Comments

112

1601145

Hammond

Marquette Trail

Bike/Pedestrian Facilities

from State St at Rabin Plaza to Toll Road overpass at Kosciusko St

9/22/2020

CMAQ Chicago UZA

2021

3_CN

$ 1,200,000

2_Low

$ 1,200,000

18 Q3 - On Track

113

1601147

Burns Harbor

Marquette Trail

Bike/Pedestrian Facilities

Marquette Greenway Trail, SR149 to Babcock Rd

8/5/2020

CMAQ Chicago UZA

2021

3_CN

$ 997,934

3_Med Funds

Q3LQR-CN est

$2,049,932 ($1,639,946 fed) CE

$0

$ 997,934

18 Q3 - Alignment set NEPA can be finalized. Q:definition of wetlands (NPS vs DNR). CN Cost increasing (2017 Q4 -TC$1,247,418 [$997,934 fed] to 2018 Q2 TC$1,747,350 [1,397,878 fed] to2018 Q3 TC$2,049,932

[1,639,946 fed]. Schedule favorable candidate for Plan B 2019 letting. CE is $0

114

1601184

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

V-Line Porter Hospital (Year #3)

CMAQ Chicago UZA

2021

5_5_FL EX

$ 264,000

1_Zero Obligated

$ 264,000

115

1601185

Valparaiso

FTA

Transfers

CMAQ Demo Operating Assistance

CMAQ Demo Chicago DASH Bus #5 (Year #3)

CMAQ Chicago UZA

2021

5_5_FL EX

$ 264,000

1_Zero Obligated

$ 264,000

116

1702158

Gary

Marquette Trail

Bike/Pedestrian Facilities

Gary Green Links/Marquette Trail. Roosevelt St to Polk St.

11/11/2020

STBG I

Chicago UZA

2021

3_CN

$ 1,000,000

2_Low

$ 1,000,000

18 Q3 - RFP process to begin shortly, no PE on Project; Verify PE & CN alotment. PE is owed for $300K May come from CN.

117

9980080

Lake County

45th Ave

Added Travel Lanes

Colfax to Whitcomb St

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 7,665,600

2_Low

$ 7,665,600

18 Q3 - NEPA almost finalized; ROW to start soon, on Track

118

1801738

Gary

Lake Street

Complete Streets Enhancement

US 12/20 & Lake St., north

7/14/2020

STBG I

Chicago UZA

2021

3_CN

$ 2,060,000

2_Low

$ 2,060,000

118

1500418

Portage

Marquette Greenway Trail

Bicycle & Pedestrian Facilities

along Ameriplex Drive

8/5/2020

TAP Chicago UZA

2021

3_CN

$ 1,495,560

4_High Funds

$ 1,495,560

18 Q3 - No ROW; TIP shows CN in TAP FHWA; SPMS shows CN in TAP Group I

119

1173427

Crown Point

101st Ave

Roadside Improvements (Drainage)

101st Ave @ SR 53

7/13/2022

STBG I

Chicago UZA

2021

2_RW

$ 200,000

4_High Executive

$ -

18 Q3 - City to decide whether or not to continue with this project. More information at next LQM. 19 Q1 - City wishes to eliminate project; will eliminate Jan 2019

120

1382598

Hobart

County Line Rd

Road Reconstruction (3R/4R Standards)

from US 6 to Cleveland Ave

10/7/2020

STBG I

Chicago UZA

2021

3_CN

$ 6,877,000

4_High Schedule

$ 6,877,000

18 Q3 - NEPA doc is outstanding. FHWA & SHPO have issues. May need to move 12 months. Pedestrian tunnel is not favored by FHWA.

121

1601846

Lake Station

Alternative Fuel Infrastructure

Public Access E-85 & CNG Station. 3P Agreement.

CMAQ Chicago UZA

2021

1_PE

$ 600,385

3_Med Executive Decision

$ 600,385

18 Q3 - City is not sure if they want to continue with this project. 18 Q4 - Flying J not interested in this project. City may decide to contine at a different location

122

1173430

Portage

Central Ave

Road Reconstruction (3R/4R Standards)

Central Ave. reconstruction from Lake/Porter Co. Line to Willowcreek Road

7/8/2020

STBG I

Chicago UZA

2021

3_CN

$ 2,080,000

4_ High Scope

$ 2,080,000

18 Q3 - project will be split in two or more phases by next LQM.

123

1173597

Munster

E-L/Pennsy Trail

Bicycle & Pedestrian Facilities

Bike/Ped Trail Connector: Erie-Lackawanna & Pennsy Greenway Trails at Cady Ditch and Marsh Ditch

7/14/2021

TAP Chicago UZA

2022

3_CN

$ 784,080

3_Med Funds

In 2019 TIP; Amend

#10 to suspend project and take out of TIP; Keep until next LQM

$ 784,080

18 Q3 - CN cost increase TC $980,100 ($784,080 fed) to TC $1,164,403 (931,522 fed) Need a new estimate since project is being tweaked and may combine with 1173707.

124

1500222

Hammond

Chicago Ave

Added Travel Lanes

from IN/IL State Line to Marble St (Phase 2)

7/9/2021

STBG I

Chicago UZA

2022

3_CN

$ 6,690,200

2_Low

Q3LQR- CN est

$5,500,000 ($4,400,000 fed); CE

$813,825 ($550,000

$ 6,690,200

18 Q3 - On track

125

1500419

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Marquette Greenway, Calumet Trail (Phase 5)

1/12/2024

TAP Chicago UZA

2022

1_PE

$ 200,000

3_Low Funds

$ 200,000

18 Q3 - Project to be suspended until later.

126

1601158

Crown Point

109th Ave

Intersect. Improvements (Roundabout)

at Iowa St

7/14/2021

HSIP Chicago UZA

2022

3_CN

$ 1,138,500

2_Low

$ 1,138,500

18 Q3 - City would like to move to FY 20 if possible. INDOT has project in 2021 STIP, but no past TIPs show this earlier than 2022 & not AM or Amend.

127

0710064

Gary

15th Ave

Signals, New or Upgraded

Multiple locations at/near intersection of 15th Ave and MLK Dr,

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 716,800

4_High Scope

18-14; #17

$ -

18 Q3 - Gary to Rescope

128

1600418

Gary

Airport Rd

Road Rehab (3R/4R Standards)

Airport Road 3R/4R Reconstruction: Cline Ave to EJ&E RR Bridge Phase 3

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 716,800

2_Low

18-14; #17

$ 716,800

129

1172078

Gary

15th Ave

Road Reconstruction

I-65 to MLK Dr.; including Michigan St. & Texas St.

7/14/2021

STBG I

Chicago UZA

2022

3_CN

$ 3,000,000

2_Low

18-14; #17

$ 3,000,000

130

1382603

Schererville

Kennedy Ave

Added Travel Lanes

Oak St to Junction St

7/13/2023

STBG I

Chicago UZA

2022

2_RW

$ 60,000

4_High Scope

$ 60,000

18 Q3 - On schedule. Part of project may become part of LocalTRAX. More after 19 Q1 LQM.

131

1173594

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Calumet Trail from Mineral Springs Rd to SR 49 (Trail Rehab)

3/2/2022

TAP Chicago UZA

2022

3_CN

$ 1,862,274

4_High Funds

Q3LQR- CN est

$1,640,342 ($1,312,274 fed); CE

$231,293 ($550,000

fed)

$ 1,862,274

18 Q3 - Not in TIP or in Spending Plan. Project was originally schedulled for FY17, but work by NIPSCO has delayed this project. Will need PE for new NEPA document (CE-4) and redo most PE. 18 Q4 - OK to move to FY 23 19 Q1 new CN amount $1,640,342 ($1,312,374 fed); CE $231,293 ($185,035 fed); Total $1,871,635 (1,497,308 fed)

132

1173427

Crown Point

101st Ave

Roadside Improvements (Drainage)

101st Ave @ SR 53

7/13/2022

STBG I

Chicago UZA

2023

3_CN

$ 1,096,415

3_Med Executive

18 Q3 - City to decide whether or not to continue with this project. More information at next LQM. 19 Q1

- City wishes to eliminate project; will eliminate Jan 2019

133

1500419

Porter County

Calumet Trail

Bicycle & Pedestrian Facilities

Marquette Greenway, Calumet Trail (Phase 5)

1/12/2024

TAP Chicago UZA

2024

1_PE

$ 1,400,000

3_Low Funds

$ 1,400,000

134

1382603

Schererville

Kennedy Ave

Added Travel Lanes

Oak St to Junction St

7/13/2023

STBG I

Chicago UZA

2024

3_CN

$ 8,198,707

3_Med Scope

FY 2024

$ 8,198,707

18 Q3 - Some funds may switch to 1383760; part of project eligable for LocalTRAX. More after 19 Q1 LQM.

Change Orders

Des #

Sponsor

Route

Work Type

Location

Letting Date

Federal Fund Type

Year

CO #

CO amount

Approval date

Comments

Amount for NIRPC

a

1601164

Hammond

Pedestrian Flashing Beacons, Installed

at 3 trail crossings

1/18/2018

HSIP Chicago UZA

2019

CO #1

$ 6,190

concurrence sent to Hammond on 5/3/2018

Total amount $6,878 ($6190.2 fed)

$ 6,190

$ 6,190

b

9707970

Lake County

45th Ave

Intersect. Improv. W/ Added Turn Lanes

at Colfax St.

8/9/2017

STBG I

Chicago UZA

1

$ 2,018.48

Received 5/29 from DA. Max amount for CO is $35,637.20

CO order Rules (approved TROC 5/29/18): Change Orders are limited to 10% of Contract or $100,000 whichever is less. Maximum amount of all change orders (for the entire program) for a year for the entire year is $375,000.

c

9707970

Lake County

45th Ave

Intersect. Improv. W/ Added Turn Lanes

at Colfax St.

8/9/2017

STBG I

Chicago UZA

2

$ 8,966.93

Received 5/29 from DA. Max amount for CO is $35,637.20

d

e

Estimated obligations


*1

$ 18,219,671

$ 3,316,262

$ 5,505,531

$ 3,990,600

$ 15,110,760

$ 1,511,040

$ 2,759,211

$ 493,680

$ 12,630,857

$ 3,553,934

$ -

$ 1,495,560

$ 27,089,600

$ -

$ 1,138,500

$ 2,846,354

$ 9,598,707

Total Change Orders

$ 245,336

$ 6,190

$ 375,000

$ 375,000

$ 375,000

Estimated and actual obligations

$ 18,465,007

$ 3,316,262

$ 5,505,531

$ 3,990,600

$ 15,485,760

$ 1,511,040

$ 2,759,211

$ 493,680

$ 13,005,857

$ 3,553,934

$ -

$ 1,495,560

$ 27,464,600

$ -

$ 1,138,500

$ 2,846,354

$ 9,598,707


2018-2021 fiscal constraint analysis

Obligation authority per funding source per fiscal year

$ 11,951,486

$ 3,607,329

$ 2,901,536

$ 984,647

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,313,202

$ 1,003,725

$ 19,177,198

FY 18 Carryover

$ 342,916

$ 83,082

$ 66,287

$ 23,257

Loans / payback from other UZAs

$ 1,450,000

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

$ -

Section 164 Penalty (included in with HSIP funds)

FY 19 = $646,110

$ 644,552

$ 644,552

$ 644,552

Bonus Funds from INDOT ([FY19-1382661,1601726,1601727,1601728][FY20-1401034])

$920,612

$ 101,162

$ 84,600

$ 734,850

Prior year obligation authority balance

$ 6,980,644

$ 2,725,616

Total obligation authority

$ 20,826,208

$ 3,690,411

$ 5,778,039

$ 1,007,904

$ 12,183,049

$ 3,677,222

$ 3,692,604

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,957,754

$ 1,003,725

$ 12,183,049

$ 3,677,222

$ 2,957,754

$ 1,003,725

$ 19,177,198

Balance (Obligation authority less estimated and actual obligations)

$ 2,361,201

$ 374,149

$ 272,508

$ (2,982,696)

$ (3,302,711)

$ 2,166,182

$ 933,393

$ 510,045

$ (822,808)

$ 123,288

$ 2,957,754

$ (491,835)

$ (15,281,551)

$ 3,677,222

$ 1,819,254

$ (1,842,629)

$ 9,578,491

Grand total obligation authority per fiscal year

$ 31,302,562

$ 20,556,600

$ 19,821,750

$ 19,821,750

Grand total of estimated and actual obligations per fiscal year

$ 31,277,400

$ 20,249,691

$ 18,055,351

$ 31,449,454

Total available obligation authority per fiscal year

$ 25,162

$ 306,909

$ 1,766,399

$ (11,627,704)

$ 9,578,491

image

image

image

image

image

*1 On Sept 18, TROC voted to move $123,474 from FY 19 C.O.s to bottom line to balance budget


image

FY 16 Change Orders =

$ 335,991

FY 17 Change Orders =

$ 182,306

FY 18 Change Orders =

$ 604,636

Average

$ 374,311

FY 16 Change Orders =

$ 335,991

FY 17 Change Orders =

$ 182,306

FY 18 Change Orders =

$ 604,636

Average

$ 374,311

Note: $6,980,644 PYB monies in 2019 are earmarked for 0710056 Total obligation authority 2018-2021 Total obligations estimated and actual 2018-2021


$ 89,035,362

$ 84,109,187

$ 4,926,175

4

New User Sign Up


To sign up as a new user, go to https://rtip.nirpc.org/secure and click on the link ‘NEW TO RegionTIP? FORGOT YOUR PASSWORD? CLICK HERE’


image


Enter in your email and check the box, then click ‘Submit’


image

Fill out all of the appropriate information and click ‘Submit New User Information’


image


You will receive an email with the subject ‘NIRPC New User Verification’ that will provide you a link to verify your email address. Click this link to verify your email; this will notify a system administrator that there is a pending user request that needs to be approved.


image


Once your account is approved by a system administrator you will receive an email notification letting you know that you can log onto RegionTIP.

Viewing Projects


image


The View Projects section of NIRPC RegionTIP lists all projects programmed in the current RTIP and those that have been submitted for amendment into the RTIP. This list of projects displays an overview of each project including the project title, type, status, implementing agency, and location. To get more details, such as funding and year programmed, click on the des. number for the specific project of interest.


The IRTIP Status column indicates whether a project is in progress, submitted, or accepted.


image

If you select ‘CREATE NEW PROJECT’ you will be taken to a screen to select which RTIP to put that new project into:


image


Once you select the RTIP, you will be taken to the screen to enter the information for this new project


image


Enter in all of the appropriate information and click ‘Save for Later’


image

The system will check to see if all of the required fields have been sufficiently filled out. If there is any information missing from the project, you will see a warning at the top of the screen to indicate it is required. That field will also highlight yellow to indicate what needs to be added.


image


Once the project has all of the necessary fields entered in, click ‘Submit To NIRPC’ to move the project forward:


image

Amending a project works in a similar way to creating a new project. Click ‘MODIFY PROJECT ON RTIP’ and select an RTIP to amend into


image


image


You will be redirected to a search page with a list of possible projects to amend. If a project shows as ‘LOCKED’ it means there is a version currently being worked on, so it cannot be amended. Choose a project with a link that reads ‘AMEND’


image

You will be redirected to a copy of the project you chose to amend. Notice that the Version of the project says Version 1, and that the ADOPTION/AMENDMENT drop-down notes the RTIP you are amending the project into


image


Make any necessary changes to the project and click ‘Save for Later’


image

Just like when creating a new project, the system will check that all the necessary fields are filled out sufficiently and let you know what is missing. Notice that since you have clicked ‘Save’, the project now shows Version 2, since you have created this new version as an amendment to the project.


image

Tracking Projects

Once a project has been submitted, whether new or amended, it will be moved into the ‘Pending’ section where it will await approval.


image


image


If your project gets denied, it will show up below the in-progress link in a section called ‘DENIED AMENDMENT(S)’.


image

Uploading Project Documents

On the project screen, click on the tab ‘Documents’ to be taken to the section to upload documents or view documents that have already been uploaded to the project.


image


To upload a document, select ‘UPLOAD DOCUMENT’


image


Fill out the date of upload, the document type, and select the file from your machine by clicking ‘Choose file’. You can add a document description as well. Once this has been filled out, click ‘Upload Selected Document’. You can upload multiple documents at once.


image

You will see the document(s) uploaded successfully with a message at the top. You can view the document by clicking on the blue link under description. You can also delete the document by clicking ‘DELETE DOC’ next to the document.


image


Once a document has been uploaded, you will see the icon logo for document next to the project all the way on the right of the project list. Click on this icon to be taken directly to the documents tab.


C:\Users\Joshua\AppData\Local\Temp\SNAGHTMLa88c356.PNG


For projects that do not have a document uploaded, you can click on the upload icon to also be taken directly to the document upload page


image